Gravel Calculator

Gravel Needed
3.46 tons
2.47 yd³ of crushed stone at 1.4 tons/yd³

1Area

Measure the footprint of the driveway, path, or pad. Split L-shapes into rectangles and add the results.

2Depth

2–3 in for a decorative top layer, 4 in for paths and pads, 6–8 in (in compacted lifts) for driveways.

3Gravel Type

Densities are typical dry values — your quarry’s ticket may differ slightly. If this gravel will be compacted as a base layer, add 10–15% to the total.

Breakdown

Area covered200 sq ft
Volume in cubic feet66.7 cu ft
Cubic yards2.47 yd³
0.5 cu ft bags (round up)134 bags
Tons to order3.46 tons
Estimates only; actual material needs vary. Density changes with moisture, stone type, and gradation — suppliers sell by weight, so confirm the tons-per-yard figure on your quote. Base layers that get plate-compacted settle roughly 10–15%; order extra to finish at your target depth.

What Is a Gravel Calculator?

Gravel is measured in one unit and sold in another. You plan a driveway or path in square feet and inches of depth, but the quarry weighs your truck and charges by the ton. A gravel calculator bridges the two: it turns length, width, and depth into cubic yards of volume, then multiplies by the density of the specific stone you picked to get tons to order. That last step matters more than people expect — a yard of light, rounded pea gravel and a yard of dense decomposed granite differ by a quarter ton, so “three yards of gravel” is not one number on the scale ticket.

How It Works

First the footprint and depth become a volume, with depth converted from inches to feet:

Volume of gravel:

Cubic Feet = Length(ft) × Width(ft) × Depth(in) ÷ 12
Cubic Yards = Cubic Feet ÷ 27

Then volume becomes weight using a typical dry density for the material — crushed stone 1.4, pea gravel 1.35, river rock 1.5, and decomposed granite 1.6 tons per cubic yard:

Tons to order:

Tons = Cubic Yards × Density (tons/yd³)

Worked Example: A 20 × 10 ft Pad, 4 Inches Deep

A 20 × 10 ft parking pad covers 200 sq ft. At 4 inches deep, that is 200 × (4 ÷ 12) = 66.7 cubic feet, or 66.7 ÷ 27 = 2.47 cubic yards. In crushed stone at 1.4 tons per yard, the order is 2.47 × 1.4 = 3.46 tons. These are the calculator’s default inputs, so the breakdown shows the same chain on load. The same volume in bagged gravel would be 134 half-cubic-foot bags — roughly 6,700 pounds hauled fifty pounds at a time, which is why anything beyond a small path goes bulk.

Compaction and Base Layers

The calculator gives you the volume of the finished layer — but gravel that gets compacted does not stay at its delivered volume. Run a plate compactor over a fresh lift of crushed stone and it consolidates by roughly 10–15% as the angular pieces lock together and the voids close. If you are building a structural base — under a shed, a paver patio, or a driveway — order that much extra so you still finish at your target depth after compaction. Deep bases should also go down in lifts: compact every 2–3 inches rather than trying to compact 6 inches at once, which only firms up the top. Note the difference by material: crushed stone and decomposed granite compact and lock; rounded pea gravel and river rock never really do, which is why they belong on top as a decorative layer, not underneath anything that needs to stay put.

Common Mistakes to Avoid

The most expensive mistake is ordering by yards when the supplier quotes tons, or vice versa, without checking the conversion — densities on quarry tickets range from about 1.2 to 1.7 tons per yard depending on stone and moisture, so confirm the figure on your quote rather than assuming. Second is skimping on depth: 2 inches of loose gravel on bare soil disappears into mud within a season; paths want 3–4 inches over a compacted base, and driveways want 6–8 inches total, laid in lifts. Third is skipping the compaction allowance on base work and coming up short after the plate compactor does its job. Finally, don’t lay gravel straight onto soft ground — a woven geotextile fabric under the stone keeps it from migrating downward and can halve how often you top up.

Frequently Asked Questions

How much area does one ton of gravel cover?

At 1.4 tons per cubic yard, a ton of crushed stone is about 19 cu ft — roughly 116 sq ft at 2 inches deep or 77 sq ft at 3 inches. Denser stone covers slightly less per ton.

How deep should a gravel driveway be?

Plan on 6–8 inches total: a base of larger crushed stone compacted in 2–3 inch lifts, topped with 2–3 inches of smaller crushed gravel. A single thin layer ruts quickly under vehicle weight.

Why does the gravel type change the tonnage?

Because suppliers sell by weight, not volume. The same 2.47 yd³ pad needs 3.33 tons of pea gravel but 3.95 tons of decomposed granite — the stone’s density, shape, and packing determine how much a yard weighs.

Do I need to add extra for compaction?

Only if the layer will be compacted. Decorative top layers can be ordered as calculated, but a plate-compacted base consolidates about 10–15%, so add that margin to finish at the intended depth.